Table 2 Input parameters for levelized unit charging costs in existing ERCOT and illustrative CAISO market for 72 MW station

From: Economic, environmental and grid-resilience benefits of converting diesel trains to battery-electric

Cost component

ERCOT

CAISO

Units

Electricity generation

Price a retail electricity provider would pay to pass through the real-time price to a retail customer, on the basis of ERCOT prices 2017–201937 and ERCOT day-ahead market clearing prices for capacity54

26.5

Illustratively modelled as the price an energy service provider would pay to pass through the real-time price to a direct-access customer, not including resource adequacy payments, on the basis of CAISO real-time prices 2017–201938, California renewable portfolio standards55, renewable energy certificate prices56 and CAISO fees57

32.9

US$ MWh–1

Transmission and distribution

T&D charges paid by a transmission-connected customer in Oncor service territory, charging only at non-critical-peak times58

0.3

T&D charges paid by a transmission-connected customer in Oncor service territory, charging only at non-critical-peak times58

0.3

US$ MWh–1

Electrical equipment

Average of best-case electric vehicle supply equipment (EVSE) costs, taken to be (1) the balance of system (BOS) costs of grid-tied storage and (2) industry-projected EVSE costs, on the basis of utility-scale solar plus storage BOS costs48 and inverter lifetime59

34.8

US$ MWh–1

Grid connection

Average levelized US grid connection cost for utility-scale solar photovoltaic (PV) projects60

2.4

US$ MWh–1

Operations and maintenance

Cost of (1) inverter maintenance for a PV plant, (2) preventive maintenance and inspection, averaged for both an existing electric bus charging station and the electrical/wiring inspection costs of a PV plant and (3) estimated structural maintenance59

4.8

US$ MWh–1

Installation

Installation costs associated with grid-tied storage, grid-connected storage cost of installation, labour and equipment, engineering, procurement and construction (EPC), overhead and interconnection48

7.5

US$ MWh–1

Capital

Return owed on capital investment, on the basis of California investor-owned utility rates of return53

7%