Table 1 Field simulation rainfall test design and times.

From: Optimizing the Dryland Sheet Erosion equation in South China

Treatment

O

B

A

Level

Carry out 9 fields each with earthworm treatment and bare plots at a slope of 10° at 0.7, 1.2, 1.6, 2.2, 2.7 mm/min or at a slope of 2°, 5°, 15°, 20° at a rain intensity of 1.6 mm/min

According to the rain intensity of 1.6, 2.2 and 2.7 mm/min at a slope of 10° or 1.6 mm/min rain at a slope of 15° and 20°, only Prunella vulgaris was planted for 4 plots

Repetition

1

1

1

Number

18

18

8

Total

44

  1. The significance level of the equation is 0.05. O is bare slope, B is Prunella vulgaris combined with earthworm planting slope, A is Single planting prunella vulgaris slope.