Table 10 Effect of changing the demand for the multiobjective problem of the unbalanced 118-bus network via ITSOA.
Method | Solution | Loss (kW) | \(\lambda\)sag (p.u) | \(\lambda\)un (%) | ENS (MWh/yr) |
---|---|---|---|---|---|
62.5% of nominal load | 14, 23, 33, 39, 43, 47, 71, 85, 87, 95, 107, 108, 121, 123, 128 | 401.773 | 1.295 | 10.312 | 75.191 |
Initial | 118, 119, 120, 121, 122, 123, 124, 125, 126, 127, 128, 129, 130, 131, 132 | 501.593 | 1.571 | 12.678 | 80.171 |
Nominal load | 14, 23, 33, 39, 43, 47, 71, 85, 87, 95, 107, 108, 121, 123, 128 | 1050.481 | 2.0930 | 16.934 | 101.306 |
Initial | 118, 119, 120, 121, 122, 123, 124, 125, 126, 127, 128, 129, 130, 131, 132 | 1322.47 | 2.549 | 23.098 | 128.274 |
125% of nominal load | 15, 22, 33, 35, 39, 41, 71, 85, 86, 95, 107, 108, 121, 123, 128 | 1843.952 | 2.769 | 21.959 | 120.161 |
Initial | 118, 119, 120, 121, 122, 123, 124, 125, 126, 127, 128, 129, 130, 131, 132 | 2109.637 | 3.218 | 26.882 | 150.343 |