Table 4 Stakeholder perspectives and Assessment Criteria across Design and Construction Phases.

From: Optimization of architectural design and construction with integrated BIM and PLM methodologies

Lifecycle Stage

Stakeholders

Current Issues

Concerns

Assessment Criteria

Design

Owner

Inaccurate budgeting, unclear classification, design flaws, and approval delays

Overall project budget and design quality

Quality

Cost

Duration

Investors

Budget overruns

Financial monitoring

Cost

Design Firms

Single-discipline design, low productivity, significant rework, and material waste

Design quality, efficiency, rework instances, and material waste rate

Quality

Waste

Duration

Cross-collaboration

Project Team Members

Poor communication and coordination difficulties

Organizational structure management

Cross-collaboration

Government Authorities

Complex approval processes, policy changes, and failure to meet energy use and environmental protection standards

Public management quality, social impact, and energy consumption

Quality

Waste

Cross-collaboration

Construction

Construction Firms

Complex safety management with diverse personnel and machinery, quality control issues, project delays, significant rework, excessive nonproductive time, and material waste

Safety, quality, duration, rework instances, and nonproductive time

Quality

Duration

Cost

Waste

Project Team Members

Team collaboration issues, unclear task allocation, complex task overlaps, and varying professional skills

Collaboration quality and task guidance

Quality

Cross-collaboration

Material Suppliers

Inaccurate project quantities or omissions, leading to untimely restocking, and impact of market price fluctuations

Construction material costs, demand, and market price fluctuations

Cost

Supervisory Units

Inconsistent construction standards, inadequate on-site management, and insufficient resources on-site affecting project progress

Construction quality and resource supervision

Quality

Cross-collaboration

Researchers

Disconnection between practice and research and sustainability issues disconnected from theoretical research

Application of theory, material waste rate, and energy consumption

Quality

Cross-collaboration

Waste

Subcontractors

Construction interface disputes, contract disputes, and delays

Contract fulfillment and unclear professional interfaces

Quality

Cross-collaboration