Table 8 Cement (replaced with bagasse ash) analysis of cost for one cubic meter.
Blends | Cement | Bagasse ash | Metakaolin | Fly ash | Total cost | Cost reduction |
---|---|---|---|---|---|---|
BA0-PP0 | 13,330 | 0 | 0 | 0 | 13,330* | 0 |
BA5-PP0 | 12,663.5 | 64.5 | 0 | 0 | 12,728* | 4.5% |
BA5-PP0-MK15 | 10,664 | 64.5 | 967.5 | 0 | 11,696* | 12.2% |