Table 1 High-speed railway subgrades settlement warning levels.

From: Settlement early warning method for high speed railway subgrades based on TD Transformer

 

1

2

3

4

Settlement (mm)

>5

4\(\sim\)5

3\(\sim\)4

<3

Velocity (mm/H)

>1.5

1.3\(\sim\)1.5

1.1\(\sim\)1.3

<1.1

Instruction

The risk is high and immediate action is needed

The risk has increased to the point where action is required

Moderate risk, need to pay attention to settlement situation

Low risk, no action required