Table 1 Power deviation details of Northern grid region on the outage event of July 2012.

From: A linear regression penalty estimator programme for the mitigation of shortcomings in availability based tariff scheme adopted in Indian power grid networks

Station details

Actual injection of power

(in MWh)

Scheduled generation of power

(in MW)

Deviation of power

(in MW)

Deviation nature

Deviation rate in percentage

Penalty rate in Rs/KWh

Singrauli

1545

1500

45

Over drawn

3%

53,766

Rihand I&II

1403

1390

13

Over drawn

0.9%

52,200

Unchahar

844

850

−6

Under drawn

0.7%

57,900

Dadri-I&II

1463

1380

83

Over drawn

0.6%

52,200

Jhajjar

415

415

0

No deviation

-

-

Shree cement

197

267

−70

Under drawn

26%

1,78,300

Dadri gas

548

538

10

Over drawn

0.1%

27,900

Auraiya gas

306

302

4

Over drawn

0.1%

27,900

Anta gas

354

349

5

Over drawn

0.1%

-

Narora

236

258

−22

Under drawn

0.8%

53,900

Nathpa jhakri

411

507

−96

Under drawn

19%

62,218

Bhakra

637

656

−19

Under drawn

0.2%

27,900

Tehri

753

760

−7

Under drawn

0.9%

58,300

Dehar

600

573

−27

Under drawn

0.4%

34,900

Chamera I

365

356

−9

Under drawn

0.2%

27,900

Salal I&II

660

601

−59

Under drawn

1%

74,900

Uri

432

430

2

Over drawn

0.4%

34,200

Pong

108

108

0

No deviation

0

-

Dulhastri

390

390

0

No deviation

0

-

Dhauliganga

282

284

−2

Under drawn

0.7%

57,900

Chamera

302

302

0

No deviation

-

-

Tanakpur

94

93

1

Over drawn

1%

74,900