Table 11 Coefficients of Independent Variables. Source: own survey 2024.

From: Determinants of road construction project delay in the case of Woliso–Ambo road construction

Model

Unstandardized coefficients

Standardized Coefficients

t

Sig

B

Std. error

beta

Coefficientsa

 1

(Constant)

0.542

0.582

 

3.930

0.007

Escalation of the material price influence

0.276

0.214

0.330

1.287

0.002

Delays in sub-contractors work influence

0.208

0.200

0.009

4.040

0.009

Material and equipment influence

0.356

0.161

0.590

2.211

0.004

Inadequate management and supervision by the consultant

0.261

0.172

0.093

1.357

0.002

Peace and security situation

0.303

0.224

0.144

4.015

0.008

  1. aDependent Variable: Road construction delay.