Table 11 Coefficients of Independent Variables. Source: own survey 2024.
From: Determinants of road construction project delay in the case of Woliso–Ambo road construction
Model | Unstandardized coefficients | Standardized Coefficients | t | Sig | ||
|---|---|---|---|---|---|---|
B | Std. error | beta | ||||
Coefficientsa | ||||||
1 | (Constant) | 0.542 | 0.582 | 3.930 | 0.007 | |
Escalation of the material price influence | 0.276 | 0.214 | 0.330 | 1.287 | 0.002 | |
Delays in sub-contractors work influence | 0.208 | 0.200 | 0.009 | 4.040 | 0.009 | |
Material and equipment influence | 0.356 | 0.161 | 0.590 | 2.211 | 0.004 | |
Inadequate management and supervision by the consultant | 0.261 | 0.172 | 0.093 | 1.357 | 0.002 | |
Peace and security situation | 0.303 | 0.224 | 0.144 | 4.015 | 0.008 | |