Table 3 Descriptive Statistics of Escalation of Material Price Influence.
From: Determinants of road construction project delay in the case of Woliso–Ambo road construction
N | Mean | Std. deviation | |
|---|---|---|---|
Descriptive statistics | |||
Construction Price Indices may overestimate or underestimate the market | 114 | 4.12 | 0.927 |
The extent of Competition in the market | 114 | 3.68 | 0.748 |
Government and Legal Regulations | 114 | 3.80 | 0.816 |
Uncompensated increase in cost of construction materials | 114 | 4.16 | 0.850 |
Client’s resist honoring the escalation clauses | 114 | 3.72 | 0.737 |
Valid N (list wise) | 114 | 3.89 | 0.815 |