Table 7 Ranking of group causes.
From: Determinants of road construction project delay in the case of Woliso–Ambo road construction
No. | Group | ∑RII | Rank |
|---|---|---|---|
1 | Escalation of the material price influence | 3.98 | 1 |
2 | Delays in subcontractors work influence | 3.69 | 2 |
3 | Material and equipment influence | 3.64 | 3 |
4 | Inadequate management and supervision by consultant | 3.60 | 4 |
5 | Peace and security situation | 3.29 | 5 |