Table 9 The change of project investment value with carbon price fluctuation.
Investment decision-making | Fluctuation rate of carbon price | |||||
---|---|---|---|---|---|---|
0.05 | 0.06 | 0.07 | 0.08 | 0.09 | 0.10 | |
Option 1 | 0 | 0 | 0 | 0 | 0 | 0 |
Option 2 | 2.7940 | 2.7941 | 2.7941 | 2.7941 | 2.7940 | 2.7940 |
Option 3 | 2.9078 | 2.9077 | 2.9077 | 2.9078 | 2.9078 | 2.9078 |
Option 4 | 5.3567 | 5.3566 | 5.3566 | 5.3567 | 5.3567 | 5.3567 |
Option 5 | −15.0967 | −15.0967 | −15.0967 | −15.0967 | −15.0967 | −15.0967 |
Option 6 | −13.9765 | −13.9766 | −13.9766 | −13.9765 | −13.9765 | −13.9765 |
Option 7 | −15.0967 | −15.0967 | −15.0967 | −15.0967 | −15.0967 | −15.0967 |
Option 8 | −23.5259 | −23.5259 | −23.5259 | −23.5259 | −23.5259 | −23.5259 |