Table 7 Project activity information.

From: Multi skill project scheduling optimization based on quality transmission and rework network reconstruction

Sports event

Serial number

S1

S2

S3

S4

S5

Number of days

Start of the project

1

0

0

0

0

0

0

Land leveling and construction of temporary facilities

2

1

2

1

1

0

6

Design phase modeling

3

1

0

1

1

0

4

Area breakdown statistics

4

1

0

1

1

1

4

Analysis of net height in key regions

5

1

1

2

0

1

8

Pre-construction risk assessment and response plan

6

1

0

1

1

0

4

Foundation construction

7

1

2

0

0

1

16

Superstructure construction

8

1

2

0

0

1

12

Construction progress monitoring and adjustment

9

0

0

1

1

1

4

Building decoration construction

10

1

2

0

1

1

16

Construction Quality Control and Interim Acceptance

11

0

0

1

0

1

6

Mechanical and electrical installation construction

12

1

2

1

0

0

14

Installation of other unit components

13

1

1

0

0

0

12

Structural acceptance of other units

14

0

0

1

0

1

4

Systematic acceptance of the project

15

1

1

1

0

1

4

End of project

16

0

0

0

0

0

0