Table 7 Project activity information.
Sports event | Serial number | S1 | S2 | S3 | S4 | S5 | Number of days |
---|---|---|---|---|---|---|---|
Start of the project | 1 | 0 | 0 | 0 | 0 | 0 | 0 |
Land leveling and construction of temporary facilities | 2 | 1 | 2 | 1 | 1 | 0 | 6 |
Design phase modeling | 3 | 1 | 0 | 1 | 1 | 0 | 4 |
Area breakdown statistics | 4 | 1 | 0 | 1 | 1 | 1 | 4 |
Analysis of net height in key regions | 5 | 1 | 1 | 2 | 0 | 1 | 8 |
Pre-construction risk assessment and response plan | 6 | 1 | 0 | 1 | 1 | 0 | 4 |
Foundation construction | 7 | 1 | 2 | 0 | 0 | 1 | 16 |
Superstructure construction | 8 | 1 | 2 | 0 | 0 | 1 | 12 |
Construction progress monitoring and adjustment | 9 | 0 | 0 | 1 | 1 | 1 | 4 |
Building decoration construction | 10 | 1 | 2 | 0 | 1 | 1 | 16 |
Construction Quality Control and Interim Acceptance | 11 | 0 | 0 | 1 | 0 | 1 | 6 |
Mechanical and electrical installation construction | 12 | 1 | 2 | 1 | 0 | 0 | 14 |
Installation of other unit components | 13 | 1 | 1 | 0 | 0 | 0 | 12 |
Structural acceptance of other units | 14 | 0 | 0 | 1 | 0 | 1 | 4 |
Systematic acceptance of the project | 15 | 1 | 1 | 1 | 0 | 1 | 4 |
End of project | 16 | 0 | 0 | 0 | 0 | 0 | 0 |