Table 3 Delivery methods ranking.

From: Innovative BWM–TOPSIS-based approach to determine the optimum delivery method for offshore projects

 

Development phase

Construction phase

Operation phase

Overall ranking

Normalized weight

Rank

Normalized Dj

Rank

Normalized Dj

Rank

DBB

0.129

5

0.142

6

0.132

5

0.135

DB

0.139

3

0.163

3

0.050

7

0.117

CMAR

0.149

2

0.169

1

0.174

4

0.164

PPP

0.107

7

0.048

7

0.185

1

0.113

BOT

0.135

4

0.152

5

0.185

2

0.157

IPD

0.219

1

0.167

2

0.178

2

0.188

EPC

0.122

6

0.158

4

0.097

6

0.125