Table 3 Delivery methods ranking.
From: Innovative BWM–TOPSIS-based approach to determine the optimum delivery method for offshore projects
Development phase | Construction phase | Operation phase | Overall ranking | ||||
---|---|---|---|---|---|---|---|
Normalized weight | Rank | Normalized Dj | Rank | Normalized Dj | Rank | ||
DBB | 0.129 | 5 | 0.142 | 6 | 0.132 | 5 | 0.135 |
DB | 0.139 | 3 | 0.163 | 3 | 0.050 | 7 | 0.117 |
CMAR | 0.149 | 2 | 0.169 | 1 | 0.174 | 4 | 0.164 |
PPP | 0.107 | 7 | 0.048 | 7 | 0.185 | 1 | 0.113 |
BOT | 0.135 | 4 | 0.152 | 5 | 0.185 | 2 | 0.157 |
IPD | 0.219 | 1 | 0.167 | 2 | 0.178 | 2 | 0.188 |
EPC | 0.122 | 6 | 0.158 | 4 | 0.097 | 6 | 0.125 |