Table 7 Parameter notations and descriptions

From: Understanding supply chain constraints for the US clean energy transition

Parameter

Description

r

Discount rate (dimensionless).

\({C}_{m,t}^{{{\rm{rm}}}}\)

Projected price for material m at time t (million $/metric ton).

\({C}_{p,t}^{{{\rm{p}}}}\)

Cost of manufacturing and installing product p at time t (million $/GW).

\({D}_{m,c}^{{{\rm{c}}}}\)

Demand for material m in producing component c (metric tons/GW).

\({D}_{c,p}^{{{\rm{p}}}}\)

Demand for component c in producing product p (units/GW).

\({R}_{o,m,t}^{{{\rm{c}}}}\)

Proportion of total pure material m available at origin o during time t (dimensionless).

\({R}_{m,t}^{{{\rm{d}}}}\)

Proportion of total available material m at time t designated for renewable energy development (dimensionless).

\({R}_{m,t}^{{{\rm{s}}}}\)

Proportion of stocked material m at time t that can be used (dimensionless).

Yo,m,t

Availability of commodities containing material m at origin o during time t (metric tons).

Xp,0

Initial installed capacity of product p (GW).

\({\overline{X}}_{t}^{{{\mathcal{K}}}}\)

Upper limit for production of category \({{\mathcal{K}}}\) during time t (GW).

\({\underline{X}}_{t}^{{{\mathcal{K}}}}\)

Lower limit for production of category \({{\mathcal{K}}}\) during time t (GW).

\({G}_{t}^{{{\mathcal{K}}}}\)

Targeted goals for cumulative installed capacity of category \({{\mathcal{K}}}\) by time t (GW).