Table 5 Comparison of the construction time for the initial design and the revised design.

From: Study on stress variation of advance fiberglass anchor bolts during tunnel excavation process

Project details

Initial design

Revised design

Number of bolts per cross-section

182

98

Time for construction of one-cycle of bolting

6 d

2.5 d

Time for excavation of one cycle and the associated advance length

3d/8 m

2d/6 m

Average tunneling speed

0.88 m/d

1.33 m/d