Table 2 Case study construction stages.
From: Framework for assessing bridges construction impact on work zone traffic using BrIM
Stages | Stages items | Start date | End date |
|---|---|---|---|
1 | Piles, pile cap, pier | 19/10/2021 | 19/12/2021 |
2 | Pier head | 9/12/2021 | 30/12/2021 |
3 | Beams erection and slabs | 20/12/2021 | 11/3/2022 |
4 | Newgersy and finishing | 20/2/2022 | 11/3/2022 |