Table 3 Travel time values of road (10th district direction).
From: Framework for assessing bridges construction impact on work zone traffic using BrIM
Stages | Road | Minimum (h) | Maximum (h) | Average (h) |
|---|---|---|---|---|
1 | Main | 0.03 | 0.11 | 0.0528 |
2 | Main | 0.03 | 0.15 | 0.069 |
2 | Detour | 0.05 | 0.13 | 0.077 |
3 | Detour | 0.05 | 0.13 | 0.074 |
4 | Main | 0.03 | 0.09 | 0.0528 |
4 | Detour | 0.06 | 0.08 | 0.0676 |