Table 7 Direct cost and duration of activity normal and crashing conditions.

From: Framework for assessing bridges construction impact on work zone traffic using BrIM

Activity

Direct cost (LE)

Duration (days)

Normal

Crash

Normal

Crash

Piles

15,028,983

19,708,806

40

30

Piles caps

9,221,826

10,069,179

28

20

Piers

6,954,401

7,217,743

19

13

Pier Head

11,645,700

12,596,987

22

17

Beams

27,582,486

27,941,508

46

35

Slabs

20,757,171

22,938,861

56

44

Newgersy and finishing

4,385,353

4,489,881

20

15

Total

95,575,920

104,962,965

145

88