Table 1 Uncertain factors affecting the progress of the water intake tunnel construction.

From: Schedule risk model of water intake tunnel construction considering mood factors and its application

Item

Specific factors

Item

Specific factors

â‘  Collapse, slippage

Collapse and slippage at the tunnel entrance or in the tunnel

â‘¥ Construction channel

Channel interruption caused by other surrounding projects

â‘¡ Rain, snow

Construction transportation interruption caused by rainfall and snowfall

⑦ Cross-coordination

Small distance blasting crossing (blasting for other subtasks nearby and blasting of adjacent tunnels)

â‘¢ Technology, safety

Surrounding important subtasks of concrete pouring and concrete curing that limit blasting

â‘§ Site handover

Delayed handover on connecting project site

â‘£ Policy factors

Holidays and shutdown of explosives supply

⑨ Other

Welcoming inspection

⑤ Concrete supply

Delayed or limited concrete supply