Table 5 Absolute construction period forecast for each critical path process (d).

From: Schedule risk model of water intake tunnel construction considering mood factors and its application

Process 1

Process 2

Process 3

Process 4

Process 5

Process 6

Construction preparation

Entrance into the tunnel

Excavation and support (inlet end and outlet end)

Lining

Grouting in the tunnel

Repair and anticorrosion

15

26

216

29

14

18