Table 6 Probability of the process stoppage based on the influencing factor.

From: Schedule risk model of water intake tunnel construction considering mood factors and its application

Item

â‘  Construction preparation

â‘¡ Entrance into the tunnel

â‘¢ Excavation and support

â‘£ Lining

⑤ Grouting in the tunnel

â‘¥ Repair and anticorrosion

â‘  Collapse, slippage

0

0

0.067

0

0

0

â‘¡ Rain, snow

0.05

0.038

0.038

0.038

0

0

â‘¢ Technology, safety

0

0.071

0.071

0

0

0

â‘£ Policy factors

0

0.035

0.035

0

0

0

⑤ Concrete supply

0

0

0

0.164

0

0

â‘¥ Construction channel

0.012

0.012

0.012

0.012

0.012

0.012

⑦ Crosscoordination

0

0

0.022

0

0

0

â‘§ Site handover

0.133

0

0

0

0

0

⑨ Other

0

0.01

0.01

0.01

0.01

0.01

Total

0.195

0.166

0.255

0.224

0.022

0.022