Table 7 Expected construction period based on \(\alpha\) and \(\beta\).
From: Schedule risk model of water intake tunnel construction considering mood factors and its application
Item index | Expected construction period (d) | |||||
|---|---|---|---|---|---|---|
\(\beta\) condition | ||||||
100 | 75 | 50 | 25 | 0 | ||
\(\alpha\) condition | 100 | 421 | 422 | 425 | 431 | 439 |
75 | 407 | 408 | 411 | 417 | 425 | |
50 | 395 | 396 | 400 | 406 | 414 | |
25 | 384 | 385 | 389 | 395 | 403 | |
0 | 375 | 376 | 378 | 382 | 388 | |