Table 4 Components specification of existing energy system components (case I).
From: Techno-economic and environmental analysis of hybrid energy system for industrial sector of Pakistan
Technology | LESCO 132 KV Grid | Fixed Capacity Genset |
|---|---|---|
Capacity (MW) | 132KV | 1 MW |
Per unit Price ($/kWh) | 0.09 | 0.23 |
Minimum Load Ratio (%) | - | 40% |
Lifetime (hours) | - | 15,000 |
Capital Cost ($) | - | 105,219.82 |
Replacement Cost ($) | - | 105,219.82 |
O&M Cost ($) | - | 10.79 |