Table 2 Key process parameters used as input data for producing primary steel via BF/BOF or DRI (according to45).
Parameter | BF/BOF | DRI/EAF (NG) | DRI/EAF (H2) |
|---|---|---|---|
SEC fuel (GJ/t) | 16.7 | 9.0 | 6.8 |
SEC electricity (GJ/t) | 1.1 | 2.1 | 1.7 |
Lifetime (years) | 20 | 25 | 25 |
CAPEX (€/tCap) | 170 | 795 | 795 |
OPEX (€/t) | 295 | 340 | 340 |
Main energy carrier | Coal | Natural gas | Hydrogen |