Table 3 Estimate at completion calculations.

From: Comparative analysis of earned value management techniques in construction projects

Method

Metric

Definition

Formula

Earned schedule method

Earned schedule (ES)

The duration of time that a project merits based on its current progress

\(ES=t+\frac{EV-{PV}_{t}}{{PV}_{t+1}-{PV}_{t}}\)

\({EAC}_{1}\)

Estimate at completion when the performance factor is equal to 1

\({EAC}_{1}=AT+PD-ES\)

\({EAC}_{2}\)

Estimate at completion when the performance factor is equal to SPI

\({EAC}_{2}=AT+\frac{PD-ES}{SPT(t)}\)

\({EAC}_{3}\)

Estimate at completion when the performance factor is equal to SCI

\({EAC}_{2}=AT+\frac{PD-ES}{SCI(t)}\)

Earned duration method

Earned duration (ED)

Amount of time accrued or earned in accordance with the project’s progress at a specific point in time

\(ED=SPI x AD\)

\({EAC}_{1}\)

Estimate at completion when the performance factor is equal to 1

\({EAC}_{1}=AC+PD-ED\)

\({EAC}_{2}\)

Estimate at completion when the performance factor is equal to SPI

\({EAC}_{2}=AC+\frac{\text{PD}-\text{ED}}{ SPI}\)

\({EAC}_{3}\)

Estimate at completion when the performance factor is equal to SCI

\({EAC}_{3}=AC+\frac{\text{PD}-\text{ED}}{ SCI}\)

Planned value method

Planned rate per time (\({PV}_{rate}\))

Predetermined pace required to complete the project within the scheduled time frame

\({PV}_{r}= \frac{BAC}{PD}\)

\({EAC}_{1}\)

The Time Estimate at Completion is a projected duration for the project under the assumption that the performance factor is 1, indicating that the remaining work will be completed as initially planned

\({EAC}_{1}\)= PD – TV

\({EAC}_{2}\)

The Time Estimate at Completion is a projected duration for the project under the assumption that the performance factor is SPI

\({EAC}_{2}=\frac{PD}{SPI}\)

\({EAC}_{3}\)

Estimate at completion when the performance factor is equal to SCI

\({EAC}_{3}=\frac{PD}{SCI}\)