Table 4 Performance factor calculations.

From: Comparative analysis of earned value management techniques in construction projects

Performance factor (PF)

Description

Formula

SPI

Schedule Performance Index

SPI = \(\frac{EV}{PV}\)

CPI

Cost Performance Index

CPI = \(\frac{EV}{AC}\)