Table 10 Optimization result for various energy systems of IEEE 69-bus in terms of NPC.
Parameter | Case-01 | Case-02 | Case-03 |
|---|---|---|---|
Cost (million $) | 40.8 | 21.05 | 20.28 |
APL(KW) | 24.72 | 63.51 | 66.79 |
Generator/MMR(MW), Loc | 2.09 (49) | 1.007 (65) | 1 (62) |
Generator (MVAR) | 1.296 | 0.624 | 0.6197 |
Solar PV(MW), Loc | 0.00 | 0.00 | 0.0013 (66) |
Wind (MW), Loc | 0.00 | 0.114 (26) | 0.0034 (29) |
Wind (MVAR) | 0.00 | 0.0707 | 0.0021 |
VMIN (p.u) | 0.973 | 0.9557 | 0.9586 |
CO2 emission (ton/year) | 12,821 | 6174 | 39.86 |
CO2 Penalty ($) | 39,772 | 19,153 | 123.64 |