Table 6 Corresponding utilization, duration and total efficiencies for each case.

From: Evaluating the planning efficiency for repetitive construction projects using Monte Carlo simulation technique

Case ID

Utilization efficiency

Duration efficiency

Total efficiency

000

0.73

0.77

0.75

002

0.78

0.76

0.77

004

0.77

0.87

0.81

200

0.86

0.91

0.88

202

0.86

0.87

0.87

204

0.84

0.83

0.84

220

0.87

0.83

0.85

222

0.82

0.86

0.84

224

0.86

0.80

0.83

400

0.91

0.92

0.92

402

0.88

0.91

0.89

404

0.87

0.87

0.87

420

0.90

0.88

0.89

422

0.88

0.90

0.89

424

0.86

0.91

0.88

440

0.93

0.86

0.89

442

0.85

0.91

0.88

444

0.86

0.87

0.86