Table 7 Performance comparison of different dynamic scheduling strategies in disturbance Scenarios.

From: Research on scheduling optimization of ship plate processing workshop based on improved NSGA-II algorithm

Disturbance scenario

Scheduling strategy

Completion time (min)

Machine load (min)

Processing cost(kW·h)

Deviation degree of the plan

Calculation time (s)

Urgent insertion

Method of this article

129.0

534.0

281.9

Medium

3.2

 

Benchmark method A (pure right shift)

135.5

545.3

285.7

Low

< 0.1

 

Benchmark Method B (Standard NSGA-II)

131.8

540.1

283.5

Medium

2.8

machine stoppage

Method of this article

130.0

514.0

297.0

High

3.5

 

Benchmark method A (pure right shift)

158.2

610.5

320.4

Low

< 0.1

 

Benchmark Method B (Standard NSGA-II)

133.5

521.7

301.2

High

3.1