Table 2 Average time for various stages of the recovery process for one-story school buildings in Central Sulawesi
Recovery phase | Average time T [days] |
|---|---|
Agreement between agencies and local authorities* | 90 |
Tender process* | 180 |
Structural design | 60 |
Building construction permit | 90 |
Reconstruction time (includes substructure and superstructure) | 180 |