Table 7 Cost and behavior of the proposed resilient BEB models

From: A resilient battery electric bus transit system configuration

Model

Base Model

Robust Model, k = 1

Robust Model, k = 2

Total annual cost (budget)

$ 6,959,381.19

$ 7,186,588.40

$ 7,524,798.35

Price of Robustness (PoR)

NA

3.26%

8.12%

Additional cost from the previous model with k − 1

NA

$ 227,207.21

$ 338,209.95

Maximum service reduction if one station fails

34.03%

0.0%

0.0%

Maximum service reduction if two stations fail

58.18%

13.73%

0.0%

Maximum service reduction if three stations fail

59.67%

22.38%

8.92%