# | Update |
|---|---|
1 | A new representation of the Blanket Shield Modules in rows #7–#12 and the explicit representations of cooling channels in 80% of the blankets |
2 | Implementation of dedicated block structure elements to facilitate local models upgrade (later called “envelopes”) for: upper port (UP) chimneys, TCWS, the Thermal Shield shrouds, the Tokamaks Dust Filter System in UP #4–#7 and ICF |
3 | The adjustment of envelopes to include the cryostat cryopump in lower ports (LP) #7 and #13 |
4 | The adaption of the correction coil envelopes to a 360° representation of the machine |
5 | The adjustment of the envelopes of Vacuum Vessel Poloidal Sector #44 penetrations in LP#01-#09-#11-#13-#15-#17 |
6 | An updated representation of UP#4-#5-#6-#7 port plug environment |
7 | The implementation of the spare pre-compression rings |
8 | The amendment of the interface between the divertor inner rail cover plate and the Blanket Shield Module #1. |