Table 3 Multiple prediction results and actual results.
From: A machine learning based EMA-DCPM algorithm for production scheduling
Item | Time (days) |
|---|---|
MLP prediction results | 3.20 |
LSTM prediction results | 4.15 |
AM prediction results | 1.02 |
Average method prediction results | 3.70 |
Actual value | 0.92 |