Table 6 Numerical results of stochastic allocation of WTs for 69-bus distribution network in scenario#2.
Item/method | Base network | MOIHHO | MOHHO | MOPSO | MOGWO | MOGOA |
|---|---|---|---|---|---|---|
WT size/@site (Bus) | -- | 801/@57/0.86 1092/@61/0.85 | 1237/@61/0.80 768/@64/0.80 | 491/@64/0.85 1435/@61/0.82 | 1116/@61/0.82 861/@64/0.93 | 1080/@61/0.87 951/@64/0.85 |
Power Loss Cost (kW) | 131,595.99 | 13770.27 | 14549.83 | 14068.05 | 14368.26 | 14459.02 |
Energy Not-provided (MWh/yr) | 11.85 | 2.91 | 3.01 | 2.95 | 2.97 | 3.04 |
WT cost ($) | -- | 880,237.17 | 903515.58 | 894,043.08 | 902624.85 | 906903.75 |
Minimum Voltage (p.u) | 0.9041 | 0.9711 | 0.9697 | 0.9705 | 0.9702 | 0.9696 |