Table 4 Indices and descriptions.
From: Dual-objective optimization of prefabricated component logistics based on JIT strategy
Indices | Descriptions |
|---|---|
p | Prefabricated component factory index,, p = 1,2,3,…,P |
s | Construction project index, s = 1, 2, 3, …, S |
y | Transportation vehicle type index, y = 1, 2, 3, …,Y |
n | Transportation trip index, n = 1, 2, 3,…,N |
a | Prefabricated component type index, a = 1, 2, 3, …,A |
Parameters | |
 M | Total number of transport vehicles |
 TPIk | Traffic congestion index for time period k |
 PNsa | Quantity of Type-a prefabricated components required for construction project s |
 Bsay | Maximum number of Type-A components that a vehicle of type y can transport per trip for construction project s |
 Dps | Distance from prefabrication factory p to the location of construction project s |
 ZTy | Loading time for transport vehicle of type y |
 XTy | Unloading time for transport vehicle of type y |
 (TWAs, TWBs, TWCs, TWDs, ) | Time window constraints for construction project s |
 DATsn | Waiting time for loading at the warehouse for the nth trip to construction project s |
 FT | Earliest departure time from the prefabricated component factory |
 YTsn | Transportation time for the nth trip to construction project s |
 DTsn | Arrival time for the nth trip to construction project s |
 DBTsn | Waiting time if the nth trip arrives at construction site s earlier than ( TWAs ) |
 DCTsn | Waiting time if the nth trip arrives at construction site s later than ( TWAs ) |
 TDTsn | Total waiting time for the nth trip to construction project s |
 LTsn | Departure time from construction project s for the nth trip |
 HTsn | Return time for the nth trip from construction project s |
 FTsn | Time point of return to the factory for the nth trip from construction project s |
 LFTsa | Time for hoisting a single Type-a prefabricated component at construction project s |
 TLFTsn | Hoisting time required for the nth trip to construction project s |
 EFi | Carbon emission factor for type i energy source |
 EAF | Energy consumption per unit shift for loading equipment |
 EAT | Total number of shifts for loading equipment |
 EBFy | Energy consumption per unit shift for transport vehicle type y during the transportation phase |
 EDF | Energy consumption per unit shift for hoisting equipment |
 EDT | Total number of shifts for hoisting equipment |
 Sn | Total number of trips required to deliver components to construction project s |
Decision variables | |
 PMsna | Number of Type-a prefabricated components loaded for the nth trip to construction project s |
 CTsn | Departure time point for the nth trip to construction project s |