Table 4 Indices and descriptions.

From: Dual-objective optimization of prefabricated component logistics based on JIT strategy

Indices

Descriptions

p

Prefabricated component factory index,, p = 1,2,3,…,P

s

Construction project index, s = 1, 2, 3, …, S

y

Transportation vehicle type index, y = 1, 2, 3, …,Y

n

Transportation trip index, n = 1, 2, 3,…,N

a

Prefabricated component type index, a = 1, 2, 3, …,A

Parameters

 M

Total number of transport vehicles

 TPIk

Traffic congestion index for time period k

 PNsa

Quantity of Type-a prefabricated components required for construction project s

 Bsay

Maximum number of Type-A components that a vehicle of type y can transport per trip for construction project s

 Dps

Distance from prefabrication factory p to the location of construction project s

 ZTy

Loading time for transport vehicle of type y

 XTy

Unloading time for transport vehicle of type y

 (TWAs, TWBs, TWCs, TWDs, )

Time window constraints for construction project s

 DATsn

Waiting time for loading at the warehouse for the nth trip to construction project s

 FT

Earliest departure time from the prefabricated component factory

 YTsn

Transportation time for the nth trip to construction project s

 DTsn

Arrival time for the nth trip to construction project s

 DBTsn

Waiting time if the nth trip arrives at construction site s earlier than ( TWAs )

 DCTsn

Waiting time if the nth trip arrives at construction site s later than ( TWAs )

 TDTsn

Total waiting time for the nth trip to construction project s

 LTsn

Departure time from construction project s for the nth trip

 HTsn

Return time for the nth trip from construction project s

 FTsn

Time point of return to the factory for the nth trip from construction project s

 LFTsa

Time for hoisting a single Type-a prefabricated component at construction project s

 TLFTsn

Hoisting time required for the nth trip to construction project s

 EFi

Carbon emission factor for type i energy source

 EAF

Energy consumption per unit shift for loading equipment

 EAT

Total number of shifts for loading equipment

 EBFy

Energy consumption per unit shift for transport vehicle type y during the transportation phase

 EDF

Energy consumption per unit shift for hoisting equipment

 EDT

Total number of shifts for hoisting equipment

 Sn

Total number of trips required to deliver components to construction project s

Decision variables

 PMsna

Number of Type-a prefabricated components loaded for the nth trip to construction project s

 CTsn

Departure time point for the nth trip to construction project s