Table 1 Key construction steps.

From: Fusing multiple source data for foundation excavation risk assessment based on cloud model and Dempster Shafer evidence theory

Working condition

Construction stage

Excavation depth (m)

1

Generate the initial stress field

2

Simulate the building load

3

Excavate the first layer of soil, construct the retaining wall, retaining pile, and lattice column

2.66

4

Erect the first support

5

Excavate the second soil layer

8.01

6

Erect the second support

7

Excavate the third soil layer

15.01

8

Erect the third support

9

Excavate the fourth soil layer

20.01

10

Erect the fourth support

11

Excavate the fifth soil layer

24.75