Table 2 Definition of project activities (duration and cost) from a real-life project.
Duration (days) | Cost (x 1,000 monetary units) | |||||
|---|---|---|---|---|---|---|
Activity | Predecessor | Min | Mp | Max | FC | VC |
Ai | – | – | – | – | – | |
Engineering | ||||||
A1 | Ai | 10 | 15 | 20 | 0 | 1.0 |
A2 | A1 | 25 | 30 | 35 | 0 | 2.5 |
A3 | A1 | 20 | 30 | 40 | 0 | 4.5 |
A4 | A2, A3 | 45 | 55 | 65 | 0 | 4.5 |
A5 | A2 | 60 | 70 | 80 | 0 | 7.5 |
A6 | A2 | 80 | 90 | 100 | 0 | 3.5 |
A7 | A1 | 50 | 70 | 90 | 0 | 10 |
Procurement | ||||||
A8 | A5 | 20 | 25 | 30 | 650.5 | 0 |
A9 | A5 | 70 | 85 | 100 | 4200 | 0 |
A10 | A6 | 70 | 85 | 100 | 3675 | 0 |
A11 | A7 | 70 | 80 | 90 | 7000 | 0 |
A12 | A7 | 100 | 110 | 120 | 75 | 0 |
A13 | A7 | 70 | 80 | 90 | 500 | 14.4 |
A14 | A11, A13 | 25 | 30 | 35 | 100 | 6 |
A15 | A14 | 12 | 15 | 18 | 0 | 6 |
A16 | A1 | 170 | 190 | 210 | 300 | 1.8 |
Construction | ||||||
A17 | A2 | 45 | 55 | 65 | 300 | 4.8 |
A18 | A17 | 50 | 60 | 70 | 550 | 5.4 |
A19 | A3 | 45 | 55 | 65 | 575 | 6 |
A20 | A3, A4 | 80 | 95 | 110 | 675 | 5.4 |
A21 | A18 | 20 | 25 | 30 | 275 | 3.6 |
A22 | A21 | 18 | 20 | 22 | 275 | 3.6 |
A23 | A18 | 35 | 40 | 45 | 287 | 4.8 |
A24 | A21 | 30 | 40 | 50 | 275 | 3 |
A25 | A8 | 35 | 45 | 55 | 75 | 8 |
A26 | A21, A25 | 75 | 85 | 95 | 125 | 9.6 |
A27 | A9, A22, A23 | 75 | 80 | 85 | 100 | 8 |
A28 | A10, A24 | 45 | 60 | 75 | 375 | 25 |
A29 | A12, A20 | 12 | 15 | 18 | 0 | 2 |
A30 | A15, A16, A29 | 50 | 60 | 70 | 75 | 7 |
A31 | A26, A30 | 12 | 15 | 18 | 0 | 3 |
A32 | A27, A28, A31 | 12 | 15 | 18 | 0 | 3 |
Af | A32 | – | – | – | – | – |