Table 3 Identification of the risks from the real-life project.
Risk | Risk Id. | Phase | Prob. | Impact (I) | Act. Imp | ||
|---|---|---|---|---|---|---|---|
Dur | Cost | (P) | Dur | Cost | |||
Technical complexity of the engineering project | R1 | Engineering | VL | L | – | 6 | |
Change of requirements in the project | R2 | R10 | Engineering | H | M | L | 2 |
Inadequate supplier management | R11 | Procurement | L | – | M | 8 | |
Supply chain disruptions | R3 | R12 | Procurement | L | H | L | 13 |
Inaccurate internal needs analysis | R4 | Procurement | M | L | – | 12 | |
Health and safety hazards | R5 | Construction | M | M | – | 20 | |
Adverse weather conditions | R6 | R13 | Construction | L | L | M | 26 |
Difficulties in obtaining permits and licences | R7 | R14 | Construction | VL | M | VL | 30 |
Availability of skilled labour | R8 | Construction | M | M | – | 28 | |
Availability of construction materials on time | R9 | Construction | L | M | – | 23 | |
Changes in the price of raw materials | R15 | Construction | L | – | H | 31 | |